Targeted investment in the production line.

A manufacturer received a proposal for a far-reaching line replacement. Novotrax helped establish which changes were needed and translated them into a functional requirements specification, clear responsibilities and measurable acceptance criteria.

Dosing station filling powder from a hopper into a bucket on a scale, with a process diagram on the worktable
Sectors
Chemicals & Process Industry
Food & FMCG
Life Sciences & Pharma
Services
Engineering Services
Business Case

The challenge

Dust, time-consuming cleaning and inconsistent fill weights were creating extra work and quality risks. A substantial supplier proposal was on the table, but internally it was not clear enough which interventions would actually solve the bottlenecks.

There were no measurable requirements for capacity, accuracy and cleaning. Nor were the boundaries between new machines, the existing installation, building works and controls clearly defined.

The question was: what do we need to change, what should that deliver, and how do we assess what is supplied?

Our approach

  1. Getting the facts on the bottlenecksTogether with production, engineering and quality, we examined the line using the process and piping diagrams. Measurements of fill weights and changeover times made the improvement task concrete.
  2. Scoping the conversion preciselyFor each process step, we determined which changes were needed. The tender focused on the necessary interventions, keeping the parts that were working well.
  3. Setting out requirements and responsibilitiesWith the internal team, we drew up a functional requirements specification covering performance, cleaning, safety and documentation. The interfaces with existing equipment and the company’s own controls standard were also set out explicitly.
  4. Making acceptance testableFor each requirement, we described how and when it had to be demonstrated: at design review, during testing at the supplier (FAT), on site (SAT) or under production conditions.

What it delivered

  • A smaller, well-founded conversion scope. Focused on the operational bottlenecks that had been identified.
  • A concrete tender package. With functional requirements, clear interfaces and defined responsibilities.
  • A basis for comparing proposals. Supplier proposals can be assessed against the same set of requirements.
  • Acceptance criteria set in advance. Clarity on the required performance and how it will be tested.

This gave production, engineering, quality and purchasing one shared basis for selecting suppliers and carrying out the work. The client could decide more precisely what to buy, why it was needed and how the final delivery would be assessed.

A major investment in your production line?

We help determine which changes are needed, which requirements go with them and how to assess what is delivered. Starting from your operations, together with your team.